СДЕЛАЙТЕ СВОИ УРОКИ ЕЩЁ ЭФФЕКТИВНЕЕ, А ЖИЗНЬ СВОБОДНЕЕ

Благодаря готовым учебным материалам для работы в классе и дистанционно

Скидки до 50 % на комплекты
только до

Готовые ключевые этапы урока всегда будут у вас под рукой

Организационный момент

Проверка знаний

Объяснение материала

Закрепление изученного

Итоги урока

Оперный театр в Сиднее

Нажмите, чтобы узнать подробности

Презентация по теме "Архитектура"

Просмотр содержимого документа
«Оперный театр в Сиднее»

Sydney opera house

Sydney opera house

Browse Sydney Opera house in Australia   Theatre in Sydney is world famous for. The popularity it gained thanks to the amazing style and stunning performances. Every year a lot of people want to see a unique build.

Browse Sydney Opera house in Australia

  • Theatre in Sydney is world famous for. The popularity it gained thanks to the amazing style and stunning performances. Every year a lot of people want to see a unique build.
Location For the construction of the Sydney Opera house was chosen a convenient location. There was provided every detail: transport, possibility to build Parking spaces. It was all done, so everyone in Australia was able to be there.

Location

  • For the construction of the Sydney Opera house was chosen a convenient location. There was provided every detail: transport, possibility to build Parking spaces. It was all done, so everyone in Australia was able to be there.
Interesting facts   There are a lot of interesting points about Sydney Opera house connected with its construction and history. The building in Sydney is related to one of the 7 wonders of the world. In 2007, it facility made the list of UNESCO. The stage of opera’s house is the largest in the world. It is made to order in France. Curtain’s area is 186 square meters. In order to light the building is required as much energy as would be enough for the city, with a population of 25,000 citizens.   Money for the construction of the opera were collected by using the  Each year it is given more than 3000 concerts.

Interesting facts

  • There are a lot of interesting points about Sydney Opera house connected with its construction and history.
  • The building in Sydney is related to one of the 7 wonders of the world. In 2007, it facility made the list of UNESCO. The stage of opera’s house is the largest in the world. It is made to order in France. Curtain’s area is 186 square meters. In order to light the building is required as much energy as would be enough for the city, with a population of 25,000 citizens.
  • Money for the construction of the opera were collected by using the  Each year it is given more than 3000 concerts.

The author of the idea The proposal to establish was received from the staff of the Symphony orchestra. It was led by Eugene Goossens. He arrived in the country as a conductor and was very surprised to learn that in Australia there is the Opera house. In 1954, a group of activists appealed to the government asking for help in organizing the space for performances. The authorities of the state considered the arguments of the musicians reasonable. History   Although, it opened not so long ago, with the base due to many events. Earlier this place located a shop for repairs of trams. Nowadays no one will remember that the amazing beauty of the building in the past — a workplace of the driver.

The author of the idea

  • The proposal to establish was received from the staff of the Symphony orchestra. It was led by Eugene Goossens. He arrived in the country as a conductor and was very surprised to learn that in Australia there is the Opera house.
  • In 1954, a group of activists appealed to the government asking for help in organizing the space for performances. The authorities of the state considered the arguments of the musicians reasonable.

History

  • Although, it opened not so long ago, with the base due to many events. Earlier this place located a shop for repairs of trams. Nowadays no one will remember that the amazing beauty of the building in the past — a workplace of the driver.
Funding   The assembling of buildings required a cash outlay that could not withstand the state budget. It was decided to organize the lottery, and money for sold tickets to be spent on construction.  Initially it was planned to spend no more than $7 million, but the construction was interrupted, the project was complex, and the money needed much more. At the time of the end of the construction took about 102 million dollars.

Funding

  • The assembling of buildings required a cash outlay that could not withstand the state budget. It was decided to organize the lottery, and money for sold tickets to be spent on construction. 
  • Initially it was planned to spend no more than $7 million, but the construction was interrupted, the project was complex, and the money needed much more. At the time of the end of the construction took about 102 million dollars.
The competition   The same year, authorities announced a contest for the best sketches of theatrical structure. It was attended by more than 200 applicants, among whom was the renowned architect Th. Watson. Initially his projects were rejected. The jury was joined by Finn E. Saarinen, who was able to convince the rest of the genius ideas of Th. Watson. The project was approved in 1957, and unfolded large-scale construction. However, the architect did not have time to follow through. He was accused of waste of money and removed from the case. Watson left the continent and was not even present at the opening. The object was completed by other architects.

The competition

  • The same year, authorities announced a contest for the best sketches of theatrical structure. It was attended by more than 200 applicants, among whom was the renowned architect Th. Watson.
  • Initially his projects were rejected. The jury was joined by Finn E. Saarinen, who was able to convince the rest of the genius ideas of Th. Watson. The project was approved in 1957, and unfolded large-scale construction.
  • However, the architect did not have time to follow through. He was accused of waste of money and removed from the case. Watson left the continent and was not even present at the opening. The object was completed by other architects.
Opera house in Sydney has its own architectural nuances. It attracts people not only by amazing performances, but because of the shape of the building, a special style. Such construction you won’t be able to see anywhere in the world. The length of the structure is 183m, and a width of 118 meters. The building is mounted on piles that are driven into the bottom of the Harbor. The feeling that it is right on the water. It took more than 500 concrete piles to keep the design. The roof was white, resembled scales and sparkled in the sunlight. Architectural features
  • Opera house in Sydney has its own architectural nuances. It attracts people not only by amazing performances, but because of the shape of the building, a special style. Such construction you won’t be able to see anywhere in the world.
  • The length of the structure is 183m, and a width of 118 meters. The building is mounted on piles that are driven into the bottom of the Harbor. The feeling that it is right on the water. It took more than 500 concrete piles to keep the design. The roof was white, resembled scales and sparkled in the sunlight.

Architectural features

The roof is made of sails   The temple of Melpomene, attracts attention primarily for its unusual roof. The idea of this design came to Watson’s mind after he saw a peeled citrus fruit.   It consists of special elements, like shells. Some people say they are more similar to white sails.  When the building is illuminated by the sun or night lights, it looks like a fabulous ship with sails floating on the endless ocean. Also, it can change colour.

The roof is made of sails

  • The temple of Melpomene, attracts attention primarily for its unusual roof. The idea of this design came to Watson’s mind after he saw a peeled citrus fruit.  It consists of special elements, like shells. Some people say they are more similar to white sails. 
  • When the building is illuminated by the sun or night lights, it looks like a fabulous ship with sails floating on the endless ocean. Also, it can change colour.
The interior and halls   Concert hall contains more than 2.5 thousand people.  Opera can attend at the same time 1.5 thousand people. Platform rotate hall; due to this, performance takes place in a special, mesmerizing atmosphere. Curtain for premises made to order. It is unique, one of a kind. Dramatic space designed for theatrical shows, ballet, and musical productions. IT have 500 seats. The play house is small in size and space. It’s used for trainings, conferences, and seminars.  Studio is the most incredible room under the open sky. It’s used for performances in avantgarde style.

The interior and halls

  • Concert hall contains more than 2.5 thousand people. 
  • Opera can attend at the same time 1.5 thousand people. Platform rotate hall; due to this, performance takes place in a special, mesmerizing atmosphere. Curtain for premises made to order. It is unique, one of a kind.
  • Dramatic space designed for theatrical shows, ballet, and musical productions. IT have 500 seats.
  • The play house is small in size and space. It’s used for trainings, conferences, and seminars. 
  • Studio is the most incredible room under the open sky. It’s used for performances in avantgarde style.